What is capacity planning in agile?

Agile capacity planning allows a team to determine how many productive hours are available for the upcoming sprint so that they can confidently commit to developing and completing a specific set of work in that time frame.

How is capacity planning done in agile?

Get the availability and time off for each person. For each person, subtract time off from Net Work Hours, and multiply the result by his availability to get his individual capacity. Add up the individual capacities to get the Team capacity in person hours, and divide by eight to get the capacity in person-days.

What is the definition of capacity in agile?

In scrum, capacity is the amount of product backlog items that a team can satisfy during a time box without going to heroic efforts. Capacity is measured by the sustainable pace that the team can achieve and that is based more on throughput of product backlog items addressed instead of number of hours you have to work.

How do I manage capacity in Jira?

To configure the capacity view:

  1. Go to your plan and select Capacity view from the dropdown next to Calculate.
  2. Select Capacity to display the capacity view. If your teams are not on the same schedule, you’ll have to select the team or person view from the timeline settings.
  3. Click on a sprint to display the details.
IT IS IMPORTANT:  How much is agility training for dogs?

Which three actions are part of the capacity planning process?

Planning for capacity breaks down into three steps: determining capacity requirements, analyzing current capacity, and planning for the future.

What are 5 Scrum values?

Scrum Values. A team’s success with Scrum depends on five values: commitment, courage, focus, openness and respect.

How is capacity calculated in Scrum?

Team Capacity is a product of the total number of Scrum team members multiplied by the number of team productive days. Here is a quick example for clarification: If your average sprint story point is 32, and you have 6 team members who are available to work (8hrs/day).

What is the difference between velocity and capacity in agile?

Velocity is a measurement of the average amount of story points delivered across a given time period. Capacity is an estimate of the total amount of engineering time available for a given sprint. … Agile development teams use this idea all the time.

How do you split user stories in agile?

Here are some of the more useful ones.

  1. Split by capabilities offered. This is the most obvious way to split a large feature. …
  2. Split by user roles. …
  3. Split by user personas. …
  4. Split by target device. …
  5. The first story. …
  6. Zero/one/many to the rescue. …
  7. The first story—revised. …
  8. The second story.

What is strategic capacity planning?

Capacity planning strategy involves the process used to determine the resources manufacturers need to meet the demand for their products or services. The level of capacity directly relates to the amount of output in the form of goods and services manufacturers can produce to satisfy customer demand.

IT IS IMPORTANT:  What is an Agile practitioner?